Decommissioning preparations began in 2007

 

  • Project start date September 1, 2010
  • Spent fuel removed from wet storage to a dry storage facility. Start demolition of Fuel Storage Building by 2014
  • Completion of plant dismantlement and site restoration work (except for the spent fuel storage facility) in 2018
  • Partial site release from NRC license in 2020
  • After the site is restored, the electrical switchyard and spent fuel storage facility will remain
  • Site ready for beneficial reuse in 2020